Smith Concrete Services has completed the critical paving operations on Seneca Street. Pervious pavers are expected to be installed in the first week of July. The completion of the paving operations as well as any sidewalks and driveways will be replaced during this time as well. Turf restoration is expected to take place within 2 weeks of the road opening.
Although Seneca street appears to be paved, we ask that residents remember this is an active construction zone. Driving on new concrete before the road is open can cause the concrete to crack and need to be replaced further pushing back the open date. Please continue to avoid the construction zone until all traffic control barricades are removed by the contractor.
The South half of Spooner Street (Phase B) is expected to be closed on the week of July 10. Door hangers will be provided to residents prior to the closing of Spooner Street. Removal of the old roadway followed by water main replacement will start once traffic control devices are in place.
Reconstruction of Seneca and Spooner Street from 10th to 12th streets
Friday, June 30, 2017
Wednesday, June 21, 2017
Tuesday, June 6, 2017
Hulstein Excavating has completed the utility installation for Phase A including water main and storm sewer. They plan to grade the road base early this week with sub-drain to follow.
Residents should keep in mind that this is an active construction site that maybe hazardous to enter. To cross the street, please go around the project eitherto the South or the North.